Schedules

NWCR Overall Schedule

A chart showing timelines to project completion for NW Campus, explained in the accompanying table

TaskPhaseStartEndComplete
OVERALLOverallJan-20Sep-2555%
Design (Huckabee)GMP-1Jan-20Sep-20100%
ConstructionGMP-1Sep-20Jan-22100%
Design (Skanska)GMP-1Mar-21Jun-21100%
Construction HubGMP-1Jun-21Mar-21100%
DesignGMP-2Jan-20Oct-20100%
ConstructionGMP-2Jan-21Aug-21100%
ProgrammingGMP-3Jan-20May-20100%
DesignGMP-3Jul-20Apr-21100%
ProcurementGMP-3Apr-21Aug-21100%
Building 1 (NW05) ConstructionGMP-3Aug-21Feb-23100%
Building 2 (NW01) ConstructionGMP-3Aug-21Aug-2376%
Furniture DesignGMP-3Feb-22Apr-22100%
Furniture Installation (Procurement in Green)GMP-3Mar-22Sep-22100%
Move (1-WCTS/WFAB/WSTU/WTLO into NW05)GMP-3Mar-23Jul-230%
Move (2-WCTS/NW05 into NW01)GMP-3Aug-23Nov-230%
DesignWA-1Feb-21Sep-21100%
Construction (Procurement in Green)WA-1Feb-22Jun-2377%
ProgrammingWA-2Feb-20Jun-20100%
DesignWA-2Jul-20May-21100%
ProcurementWA-2Jul-22Nov-22100%
WATB Renovation, GreenhouseWA-2Nov-22Apr-2367%
Furniture Installation (WATB)WA-2Apr-23May-230%
Move (1-WFAB/WSTU/WTLO to WCTS)WA-2Mar-23Jun-230%
Move (1-WFAB/WSTU to WATB)WA-2Mar-23Jun-230%
Move (1-WFAB to WFSC)WA-2Mar-23Jun-230%
Demolition (WTLO/WSTU/WFAB)WA-2Jun-23Nov-230%
Move (2-WCTS/NW05 into NW01)WA-2Jul-23Nov-230%
Demolition (WCTS)WA-2Oct-23Jan-240%
ProgrammingGMP-4Jan-20May-20100%
DesignGMP-4Jul-20Jul-21100%
ProcurementGMP-4Jun-23Oct-230%
WHPE/WBSA/WACB RenovationGMP-4Nov-23Jun-240%
Building 3 (NW03) ConstructionGMP-4Nov-23Jun-250%
Building 4 (NW02) ConstructionGMP-4Nov-23Jun-250%
Furniture DesignGMP-4Apr-24Jun-240%
Furniture Installation (Procurement in Green)GMP-4Aug-24Dec-240%
Move (3-NW01/NW05/WATB/WFSC to NW02 & NW03)GMP-4Aug-25Sep-250%

SECRE Overall Schedule

A chart showing timelines to project completion for SE Campus, explained in the accompanying table

TaskPhaseStartEndComplete
OVERALLOverallSep-20Jul-2551%
DesignWA-1Jul-21Nov-22100%
ConstructionWA-1Nov-22Sep-22100%
Design (Buildings SE01 and SE07)GMP-1Sep-20Apr-22100%
ProcurementGMP-1Feb-22Jul-22100%
Construction (Student Experience Building SE01)GMP-1Jun-22Nov-2349%
Construction (Academic Building SE07)GMP-1Jun-22Nov-2349%
Design (Furniture)GMP-1Apr-22Dec-22100%
Furniture (Procurement in Green)GMP-1Jan-23Feb-2410%
Move (Procurement in Green)GMP-1May-23Mar-240%
DesignWA-2Apr-22Jul-22100%
Construction (Procurement in Green)WA-2Mar-23Dec-230%
FurnitureWA-2Dec-23Feb-240%
MoveWA-2May-23Mar-240%
Design (Renovations)GMP-2Sep-20Aug-22100%
Construction (Procurement in Green)GMP-2Sep-23Apr-250%
Design (Furniture)GMP-2Apr-22Nov-22100%
Furniture (Procurement in Green)GMP-2Jul-24Jun-250%
Move (Procurement in Green)GMP-2Sep-24Jul-250%