Schedules

NWCR Overall Schedule

TaskPhaseStartEndComplete
OVERALLOverallJan-20Jan-2655%
Design (Huckabee)GMP-1Jan-20Aug-20100%
ConstructionGMP-1Sep-20Dec-21100%
Design (Skanska)GMP-1Mar-21May-21100%
Construction HubGMP-1Jun-21Feb-22100%
DesignGMP-2Jan-20Oct-20100%
ConstructionGMP-2Jan-21Aug-21100%
ProgrammingGMP-3Jan-20Apr-20100%
DesignGMP-3Jun-20Mar-21100%
ProcurementGMP-3Apr-21Jul-21100%
Building 1 (NW05) ConstructionGMP-3Aug-21Feb-23100%
Building 2 (NW01) ConstructionGMP-3Aug-21May-2376%
Furniture DesignGMP-3Feb-22Mar-22100%
Furniture Installation (Procurement in Green)GMP-3Apr-22Jul-22100%
Move (1-WCTS/WFAB/WSTU/WTLO into NW05)GMP-3Feb-23May-230%
Move (2-WCTS/NW05 into NW01)GMP-3Jul-23Oct-230%
ProgrammingWA-2Feb-20Apr-22100%
DesignWA-2Jul-20Apr-21100%
ProcurementWA-2Jul-22Oct-22100%
WATB Renovation, GreenhouseWA-2Nov-22Apr-2367%
Furniture Installation (WATB)WA-2Apr-23Apr-230%
Move (1-WFAB/WSTU/WTLO to WCTS)WA-2Feb-23May-230%
Move (1-WFAB/WSTU to WATB)WA-2Feb-23May-230%
Move (1-WFAB to WFSC)WA-2Feb-23May-230%
Demolition (WTLO/WSTU/WFAB)WA-2Jun-23Feb-240%
Move (3-WCTS/NW05 into NW01)WA-2Jul-23Oct-230%
ProgrammingGMP-4Jan-20Apr-20100%
DesignGMP-4Jun-20Jul-22100%
ProcurementGMP-4May-23Oct-230%
Building 3 (NW03) ConstructionGMP-4Nov-23Sep-250%
Building 4 (NW02) ConstructionGMP-4Nov-23Oct-250%
Furniture DesignGMP-4Apr-24May-240%
Furniture Installation (Procurement in Green)GMP-4Aug-24Dec-250%
Move (4-NW01/NW05/WATB/WFSC to NW02 & NW03)GMP-4Sep-25Jan-260%

 

SECRE Overall Schedule

TaskPhaseStartEndComplete
OVERALLOverallOct-20Dec-2571%
DesignWA-1Jul-21Oct-22100%
ConstructionWA-1Nov-22Aug-22100%
Design (Buildings SE01 and SE07)GMP-1Oct-20Mar-22100%
ProcurementGMP-1Feb-22May-22100%
Construction (Buildings SE01 and SE07)GMP-1Jun-22Dec-23100%
Activation / CommissioningGMP-1Dec-23Jan-24100%
Relocate Culinary Equipment (Building SE07)GMP-1Dec-23Feb-24
0%
Branding GraphicsGMP-1Jan-24Mar-240%
Delivery and Install Electrical SwitchgearGMP-1May-24May-240%
Design (Furniture)GMP-1Apr-22Nov-22100%
Furniture (Procurement in Green)GMP-1Jan-23Mar-24100%
Move (Procurement in Green)GMP-1Apr-23Feb-2494%
DesignWA-2Apr-22Jul-22100%
Construction (Procurement in Green)WA-2Mar-23Dec-23100%
ActivationWA-2Nov-23Jan-240%
MoveWA-2Oct-23Feb-2494%
Design (Renovations)GMP-2Oct-20Aug-22100%
Construction (Procurement in Green)GMP-2Sep-23Apr-2528%
Activation / CommissioningGMP-2May-25Aug-250%
Restoration of Swing SpacesGMP-2Nov-25Dec-250%
Design (Furniture)GMP-2Apr-22Oct-22100%
Furniture (Procurement in Green)GMP-2Jul-24Jul-250%
Move (Procurement in Green)GMP-2May-25Sep-250%